Shell Haven - London Gateway Project

BPH Equipment supplied a crawler crane and various piling equipment to the London gateway project.

BPH Equipment supplied a crawler crane and various piling equipment to the London gateway project.

This was a difficult project which BPH Equipment followed through for a duration of around one year.

Two PTC 65HD RK Vibrodrivers supplied by BPH Equipment were used to partially drive around 70-80 raked [1:3] and over 300 vertical casings.                                                                                                                                   

The raked casings had a diameter of 1067mm and the vertical casings had a diameter of 916mm.

The two impact hammers used were a Junttan HHK 14A [14t drop weight] for the raked casings and a Junttan HHK 9s [9t drop weight] for the vertical casings.

The crane supplied for this job was a Kobelco CKE 1800 [180t lifting capacity] 